In order to meet the energy needs of the large investment projects implemented and to be implemented in the Kiskunfélegyháza area, NKM Áramhálózati Kft. has decided on the complete primary reconstruction of the Kiskunfélegyháza station.

After tendering, Forest-Vill Kft. was commissioned to carry out the primary and secondary works of the substation reconstruction, as well as the architectural works.

Construction began last year, and 50% of the station has been reconstructed so far.